gridConnectionCompletionDate

P34483 predicate

Indicates the date on which a connection to the electrical grid is fully completed and becomes operational.

Aliases (2)

  • gridConnectionDate ×4
  • gridConnectionYearUnit1 ×1

Sample triples (6)

Subject Object
Gwynt y Môr Wind Farm 2014
Hatch Nuclear Power Plant 1974 via predicate surface "gridConnectionYearUnit1"
Vogtle Electric Generating Plant
surface form: "Vogtle Unit 1"
1987 via predicate surface "gridConnectionDate"
Vogtle Electric Generating Plant
surface form: "Vogtle Unit 2"
1989 via predicate surface "gridConnectionDate"
Vogtle Electric Generating Plant
surface form: "Vogtle Unit 3"
2023 via predicate surface "gridConnectionDate"
Vogtle Electric Generating Plant
surface form: "Vogtle Unit 4"
2024 via predicate surface "gridConnectionDate"