Milestone B is a key decision point in the U.S. defense acquisition process that authorizes a program to enter the Engineering and Manufacturing Development phase.

Try in SPARQL Jump to: Surface forms Statements Referenced by

All labels observed (1)

Label Occurrences
Milestone B canonical 3

Statements (48)

Predicate Object
instanceOf Defense Acquisition Board milestone
U.S. defense acquisition milestone
acquisition decision point
appliesTo Department of Defense acquisition programs
associatedWithPhase Engineering and Manufacturing Development
authorizes entry into Engineering and Manufacturing Development
country United States of America
surface form: United States
decisionAuthority Milestone Decision Authority
follows Milestone A
governedBy Adaptive Acquisition Framework policies
DoD Instruction 5000.02
surface form: DoD Instruction 5000 series

DoD Instruction 5000.02
surface form: DoD Instruction 5000.02 (historical versions)
governsEntryTo Engineering and Manufacturing Development phase
involves assessment of cybersecurity and program protection
assessment of integration risks
assessment of manufacturing readiness
assessment of sustainment planning
assessment of technology readiness levels
assessment of test adequacy
review of cost schedule and performance risks
marksTransitionFrom Technology Maturation and Risk Reduction phase
marksTransitionTo Engineering and Manufacturing Development phase
mayBeSupportedBy Defense Acquisition Board (through representation)
surface form: Defense Acquisition Board
objective commit program to development
confirm program affordability
confirm program executability
establish program baseline for cost schedule and performance
overseenBy Milestone Decision Authority
partOf U.S. defense acquisition system
surface form: Department of Defense acquisition framework

U.S. defense acquisition system
precedes Milestone C
requires Technology Maturation and Risk Reduction completion
affordability assessment
approved Acquisition Program Baseline
approved Acquisition Strategy
independent cost estimate
life-cycle sustainment planning
program protection planning
risk management plan
sufficient technology maturity
systems engineering plan
test and evaluation strategy
updated capability requirements validation
resultsIn approval to award Engineering and Manufacturing Development contracts
establishment of Acquisition Program Baseline
formal program initiation for many programs
usedIn Major Defense Acquisition Programs
other significant defense acquisition programs

Referenced by (3)

Full triples — surface form annotated when it differs from this entity's canonical label.

Defense Acquisition Board (through representation) convenesAt Milestone B
subject surface form: Defense Acquisition Board
Milestone A precedes Milestone B